The site is bound by Surf Drive to the north, Peaceful Bay to the south and existing developments to the west and east.
The Client’s intention was to deliver the three stages in one package, however the size of the scope and market demands meant construction occurred in the following packages:
JDSi reported to the Client’s project manager and ensured successful negotiations were carried out with neighbouring developers for tying into road and drainage networks.
Upgrade of the existing roads were a key part of our Client’s scope. This was our Client’s first subdivisional project and JDSi ensured all interfacing issues were managed promptly and efficiently for the benefit of all parties involved.
The bulk earthworks design was optimised to be carried out for the complete three stages. JDSi successfully managed all remediation and demolition issues prior to the commencement of bulk earthworks.
The Contractor selected by the Client was also a new entity to this project. JDSi had to ensure any and all risk was managed by being proactive and keeping the Civil Contractor accountable. The professional relationship between the Client, JDSi and Contractor was highly ethical and mutually respectful. The project team was able to successfully delivery the three stages within Client’s required timelines and market requirements. The positive collective feedback from the Water Corporation and the City of Rockingham reflected the high end product being delivered for this estate by the project team.